top of page

Project Managers and Safe Crane Lift Guidance

  • 17 hours ago
  • 6 min read
Creating a Safe Site for Crane and Lifting Operations

Lifting operations are common on construction and infrastructure projects, but they also present significant risk. Cranes and lifting devices can move heavy loads through complex environments, often in close proximity to workers, structures, and public areas.


Many lifting incidents occur not because of technical crane failures, but because the lifting task or the site conditions were not properly considered.

This guidance provides practical direction for Project Managers responsible for worksites where lifting operations occur. It helps Project Managers understand their role in ensuring that lifting activities are conducted safely, regardless of crane type.


The principles apply to all lifting operations, including:


• Mobile cranes

• Tower cranes

• Crawler cranes

• Truck loader cranes (Hiabs)

• Pick-and-carry cranes

• Hoists and mechanical lifting devices


While crane operators and lifting specialists manage the technical aspects of lifting, Project Managers play a key role in ensuring the worksite environment and task conditions allow for safe lifting operations.


The 5 Components of a Safe Lift

  1. The Project Manager’s Role in Lifting Operations


The Project Manager is responsible for ensuring that the worksite supports safe lifting activities.


Project Managers are not expected to design or engineer the lift. However, they must ensure that lifting operations are properly planned and that site conditions match the lift plan.


This includes confirming that:


  • the lifting task is clearly understood

  • competent lifting personnel are engaged

  • the lift plan reflects actual site conditions

  • lifting activities are coordinated with other work on-site

  • site hazards that could affect lifting operations are identified and managed


In many lifting incidents, the lift plan itself was technically correct, but the task conditions or site environment were not properly considered.


Key responsibilities of the Project Manager include:


Provide safe site conditions

Ensure ground conditions, underground service clearance, energy sources such as power, access routes, and working areas are suitable for crane operations.


Review lift plans

Confirm the lift plan reflects actual site conditions and the work being performed.


Manage site interfaces

Coordinate lifting activities with trades, deliveries, and other site operations.


Control access

Establish exclusion zones and manage pedestrian and vehicle movement.


Ensure communication

Confirm that lifting team roles are defined and communication systems are in place.


Support lifting supervision

Ensure competent supervision is present when required.


  1. The Five Components of Any Lift


Every lifting operation involves five interacting elements.


Understanding these elements helps Project Managers review whether a lift can be carried out safely.


Component

Description

Typical Responsibility

Task

The work activity being performed

Project Manager / Principal Contractor

Load

The item or material being lifted

Builder, supplier, manufacturer

Lifting Method

The rigging arrangement used to connect the load to the crane

Dogman/rigger

Crane

The lifting equipment performing the lift

Crane provider/Crane Operator

Site Environment

Ground conditions, underground services, energy sources, site layout, hazards, and surrounding activities

Project Manager


A lifting operation becomes unsafe when any one of these elements is poorly understood or incorrectly controlled.


Project Managers usually have the greatest influence over two of these elements:


  • the task being performed

  • the site environment where the lift occurs


These factors strongly influence whether lifting can occur safely.


  1. Understand the Task


Effective lift planning begins with understanding the full task the crane is supporting.


The task is not limited to the lift itself. It includes the activities that must take place before, during, and after the lift to ensure the work is completed safely. The crane should be treated as a tool being used to carry out the task.


Understanding the task helps determine:


  • the lifting method required

  • the crane and lifting equipment needed

  • the sequence of work

  • the people, plant, and equipment involved

  • the hazards, risks, and controls associated with the activity

  • the level of planning, coordination, and supervision required


Project Managers should confirm:


  • what work activity is the crane supporting

  • how the activity will be carried out, step by step

  • what must occur before the lift, during the lift, and after the lift

  • where the load is being lifted from and where it will be placed

  • whether the lift is a one-off activity or repeated multiple times

  • whether workers will need to guide, land, position, connect, or secure the load

  • what documents and controls are required for the task, such as a JSA, SWMS, permit, exclusion zone, or traffic management plan


Project Managers should also identify other hazards and site activities that may affect the lift, including:


  • movement of vehicles, mobile plant, including items like mobile elevated work platforms or equipment

  • pedestrians or workers in adjacent areas

  • other trades or activities operating nearby

  • restricted or congested work areas

  • overhead or underground services

  • changing ground, access, or site conditions


The task should be broken into clear steps so hazards can be identified and controls can be applied at each stage of the activity.


As task complexity increases, the level of lift planning, coordination, and supervision must also increase.


  1. Confirm the Load


Once the task is understood, the next step is confirming the load.


Before lifting begins, the load weight must be known or verified.


Key questions include:


  • What is the weight of the load?

  • How was the weight determined or verified?

  • Where is the centre of gravity?

  • What lifting points will be used?

  • Will the load remain stable during lifting?


Common load-related risks include:


  • unstable pallets

  • uneven weight distribution

  • shifting or poorly secured materials

  • loads that may break apart during lifting

  • materials that may slide or separate

  • sharp edges that can cut or damage rigging

  • lift points not suitable for the load


Understanding the load weight and centre of gravity is essential for selecting the appropriate crane and rigging configuration.


  1. Review the Lifting Method


The lifting method describes how the load is connected to the crane.


A lift plan should clearly identify:


  • lifting gear type

  • sling configuration

  • lifting points

  • load balance (centre of gravity)

  • rigging capacity


Rigging capacity must exceed the load weight and account for sling angles and load distribution.


Incorrect rigging is one of the most common causes of dropped loads.


The shape of the load and its centre of gravity largely determine the appropriate rigging arrangement.


  1. Confirm the Crane is Suitable


The crane selected for the lift must be capable of safely lifting the load at the required radius and height.


When reviewing the lift plan, confirm:


  • crane type

  • crane capacity

  • working radius

  • boom configuration

  • counterweight configuration

  • lifting height


Crane capacity changes significantly as the working radius increases.


A crane capable of lifting a load close to the crane may not be able to lift the same load at a greater distance.


  1. Check the Site Environment


Site conditions often determine whether a lift can be carried out safely.


Project Managers should confirm that the worksite environment supports the lifting operation.


Ground conditions


Confirm:


  • ground bearing capacity

  • soil stability

  • recently excavated or backfilled areas

  • proximity to trenches or underground services

  • use of outrigger pads or crane mats


Ground stability is critical to crane safety.


Site layout


Check for potential obstructions such as:


  • nearby structures

  • scaffolding

  • overhead services or power lines

  • restricted access areas

  • adjacent public spaces


The lifting path should be clear from the pick-up point to the placement location.


Exclusion zones


Confirm:


  • exclusion zones around the crane

  • drop zones beneath suspended loads

  • pedestrian controls

  • traffic management where required


No person should stand beneath a suspended load.


Weather conditions


Weather conditions can significantly affect lifting operations.


Risks include:


  • high wind

  • sudden gusts

  • reduced visibility

  • rain affecting ground stability


Large or lightweight loads are particularly sensitive to wind. See Crane Association Wind Speed Safety. Mancage work the limit is 7 m/s.


  1. Practical Lift Review Method


Project Managers can quickly review lifting operations using five simple questions:


  1. Is the lifting task clearly understood?

  2. Is the load known and stable?

  3. Is the lifting method appropriate?

  4. Is the crane suitable for the lift?

  5. Is the site environment safe for the operation?


If any of these questions cannot be clearly answered, the lift should be reviewed before work proceeds.


Crane Hazards Wheel

  1. Common Causes of Lifting Incidents


Many lifting incidents occur due to predictable failure points.

Cause

Description

Ground failure

Crane instability due to inadequate ground support

Overloading

Crane capacity exceeded

Incorrect rigging

Load poorly attached or unbalanced

Wind effects

Load movement caused by wind forces

Inexperience

Personnel unfamiliar with lifting risks

Equipment failure

Mechanical or structural failure

Dropped objects

Materials falling from loads


Understanding these failure mechanisms helps Project Managers recognise unsafe lifting conditions early.


  1. When a Lift Should Be Stopped


A lifting operation should be stopped if:


  • the lifting task is unclear

  • the load weight cannot be verified

  • rigging methods are uncertain

  • crane configuration differs from the lift plan

  • ground conditions appear unsafe

  • exclusion zones are not established

  • weather conditions exceed safe limits

  • communication between personnel is unclear


Stopping a lift when uncertainty exists is an important safety control.


Core Principle


A lifting operation is safe only when five elements are controlled at the same time:


  1. The task is understood

  2. The load is known and stable

  3. The lifting method is correct

  4. The crane is suitable

  5. The site environment is controlled


Project Managers play a central role in ensuring that the task and the site environment allow for safe lifting operations.

Comments


bottom of page